Restorations and Additions of Classic 1880s Summer house

The Summer House project has reached its completion. Below are photos that show the before, during and final results.

Click on photos for more detail


The above photo shows the original state of the house
with attached laundry room and garage at the rear of the house.


 
Views of original laundry room and garage.
 
 
 
Demolition begins!
Laundry Room/Garage are removed.

 
 

Digging out for the new foundations.
Installing beams prior to raising house.
 
Details!
 
We're ready for final excavation and start of new cellar forms and foundations.
 
Shown above, foundations with sill sealer, termite shield and 2 x 10 PT joists
plus embedded hardware which involves prep for lowering older home.

 

View of terrible condition of underside
of porch which will probably be replaced
pending more thorough examination.

View of the set up for concrete cutting to correct
concrete foundation subs mistake. Set up with
big blade cut and level. The foundation "as built",
as submitted to building and conservation,
showed absolutely perfect horizontal work.

Sometimes things happen but the advantage
of working with a well known form person is that
they will correct everything on their dime.

 

The cellar picture above shows new fire place chimney base, together with more concrete footings for steel posts that would support the main first floor underside structural areas of the existing older home.

The 2 photos above show the older structure resting on new foundation and the concrete form repair, to correct prior misjudgment by form contractor.


Weather permitting, cribbing and steel beams under new cellar to be removed later this week, after final sill perimeter shimming.
Confirmed all interior doors and windows still easily operable and working as before when house was on granite posts and cyprus poles.

Please note the chimney base treatment.
After the steel is removed the mason will
complete the final filling in of the chimney
base for the fireplace.

The crew sets steel columns under old framing junctions originally supported by
the granite posts.

We have exercised our option of utilizing
more steel posts to secure the older part
of the main house and fewer manufactured
beams. Its a better structural
technique overall.

Interior structural repairs under old house.
   
Initial 1st floor addition framing.
We work year round.
   

Framing second floor and completely
rebuilding older 1st floor porch area
(see bottom left).

Other view of framing second floor. 1st floor windows are framed out, but not
cut out of walls yet to afford some protection from winter winds.
     
Exterior framing and steel.
Preparation for sidewall around the sun
porch with velocity zone straps as required.
Older building perimeter skirts: sheathing,
flashing, new trim & side wall. We will be
grading up around the foundation after we
reset the finished lawn level. Area on left
bottom on piers due to velocity zone and
Commonwealth DEP regulations. The rest
of the area involves a full cellar foundation.
   
Measuring tape on right
showing height of cabinetry.
The utility chase removal on the stair landing
wall provides over 45" of space. The plans
discussed moving the wall out another 14".
     
Older house wall reflecting framing deficiencies to be corrected.
Rough Stairway up, including winders,
showing how it will fit.
     
 

Pictures below of new addition, gable end and side wall views.

Pictures below of second floor and preliminary roof framing. Please note the picture of the gable end near
dirt pile shows an outline of two circular windows and a special bay window.

     
   

Removing existing chimney due to safety
issues and age. It will be rebuilt and reflashed

as we continue the whole house reroofing in
red cedar. Stay tuned...

Mock up for roof addition cupola design
   
Note the revised shower placement and
size as discussed for the 2nd. floor.
Some of the new trim installations.
    
Master carpenter fabrication of lead
coated copper roof cricket to be installed.
Cricket installed where 3 roof areas
converge, which will shed water
during downpours.
Upper cricket area, again designed to shed
water and divert from adjacent sidewall
and window casing on older part of house.
   
Long view of cricket locations showing the roof slopes that converge in those areas where
they are installed with the new red cedar roofing and white cedar sidewall. With heavy rain
or snow and three roof levels falling moisture downward perhaps driven by heavy winds,
these crickets are another level of flashing detail and workmanship that allow specific
design executions to be moisture free always. Architects design and Builders create
the finished and final product and make everything work correctly.
   
Starting framing for bedroom deck
   
Continuing bedroom deck.
More exterior trim.
NOW , the windows.
   
Final result of main gable end incorporating
client, builder and architect ideas.
Building is a cooperative venture.
    
 
Adapting old house area trim
to replicate new addition.
   
Roadside View
Side View - Dennis, our roofer, installing
red cedar shingles. Hand nailed with
stainless steel shingle nails according
to shake and cedar institute
specifications. The only way we
work, according to directions.
   
Pocket Door View- Frame and installation.
Plumber and electrician - Rough plumbing
and electrical being installed in
the new kitchen.
   
Sidewall and picture of cheek sidewall.
Cheek flashing as an adjunct with red cedar roofing
.

View of kitchen, with icynene open cell foamed installation( a green product in many ways). All rough plumbing and electrical are completed and the next step after local building inspection for the installation will be plaster and soon after radiate heating and tiles for floors and then kitchen cabinet installations. Stay tuned....

     
Kenny the plumber installing radiate heat tracks under sub floor of which the above area are the winter/summer area transition. The project involves most of the new addition being operational year round at this stage.
Marty and Bryant completing multiple window gable trim and finish.
     
Plumbers installing radiate floor
heating in new kitchen.
Fireplace hearth view
of new family room.
Beginnings of the main entrance area.
     
Startings of interior trim.
Installing kitchen cabinets.
Finish painting in upper bedroom.
Awaiting installation of future
radiant heat and oak floors.
 
Tiling on side porch main entrance area.

Kenny in the cellar with furnace installation
and hook ups to multi floor
level radiant heating.

Pandemonium in the new kitchen.
Setting appliances, finishing granite
counters. Interested observer...

 
 
Kitchen window trim and hanging door.
Main Stair platform done in rift and
sawn oak flooring, under which we have
installed radiate heating elements.
Will finishing circle window
in new family room
 
     
Final kitchen tiling above stove,
painter completing closet
   
      
Completed exterior view on
a sunny Cape Cod day

 

View of a now active kitchen area.
Transition area hall bookcase areas.
Family room fireplace mantel and
bookcases in process.
   

Alec completing finish sanding. There
are three levels of sanding after wood flooring is installed. The next
steps would be flooring sealer with an oil based product, followed by multiple floor finishing coatings with buffing in
between to give us a final product.

NOTE: Alec's sanding system is
completely dustless, which saves
labor for final clean up.
Note the flooring ready to be initially
coated and the finished bump
out window in the family room.
   

Photographs of the finished interior

 
     

We returned in the Winter to install baseboard heating panels on three floors and on the sunporch in the older, restored part of the house.

Framing and opening walls for routing the
hot water piping through floors.
Older section of house - setting
heat pipes for two floors in
wall & ceiling cavities.
Piping through wall
     
Setup and pre-painting before panels
go up on the outside wall.
New heat/baseboard hotwater panels
in the restored section of the house.
     
   
  Example of heat elements
and small width baseboard
to left of door in sun porch area.
 
   
   

The Summer House project has reached its completion.
Above are photos that show the before, during and final results.

Return to Project Gallery

 

 
Employee Owned & Operated

We educate, advocate and include sustainable energy features where possible with all of our renovation,
new building and restoration projects. We are facilitators of sustainable and energy saving building & renovation practices since the early 1980's.

EPA Certified Firm

We are facilitators of
Passive House Design Principals

HOME  |  SAMPLE PROJECTS  |  ABOUT US   |  CONTACT US

Contractor Supervisor License #016018
Home Improvement Contractor #100011
City of Boston Building License #B20374
EPA Certified #NAT 21989-0

Cape Painting and Carpentry, Inc.
P.O. Box 39
North Falmouth, MA 02556-0039

Owner
Peter Kroll
508-564-3298
pmarshallk@aol.com